Installation steps of the chiller
(1) The chiller should be installed directly on the horizontal plane, do not install it upside down, obliquely or vertically.
(2) To generate heat when the chiller is running, the circulation of cooling air should be ensured, and a certain space should be left around during installation, and the heat generated will be dissipated upward, so do not install it around heat-labile equipment.
(3) The chiller cannot be installed in places with various fibers, paper chips (chips), metal fragments, etc.
The water outlet of the chiller should be connected with the water inlet of your instrument, and the water outlet of your instrument should be connected with the water inlet of the cooling circulating water machine.